B Branch Track Upgrades 100% Complete

Updated on July 6, 2022

On Friday, July 1, we completed work on the B Branch full access closure. This project improved safety and reliability for riders, pedestrians, bicyclists, and drivers while minimizing disruption.

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

What We've Accomplished

an infographic illustrating that during the 12 days of work, crews replaced 3200 feet of track, four special trackwork units, upgraded a vehicle intersection, upgraded a pedestrian crossing, installed gltps equipment, and did additional work like concrete repairs, painting, and fence repairs

In these 12 days, our crews completed the following:

  • Renewed 3,200 feet of track
  • Upgraded four special trackwork units
  • Installed Green Line Train Protection System components along the entire B Branch
  • Upgraded the Linden St vehicle intersection and the Fordham Rd pedestrian crossing
  • Completed additional work beyond the original scope, including concrete repairs at Babcock St and Amory St stations, track replacement in Lake St yard, painting, fence repairs, and lighting improvements

Contact Us

For questions and comments related to Green Line track upgrades, please email the Green Line Transformation team at GLT@mbta.com.

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects