Intersection Upgrades 70% Complete

Updated on October 21, 2019

As part of the Capital Acceleration Plan, we’ve expedited Green Line and Mattapan Line intersection upgrades to bring you a safer, more reliable MBTA experience.

We’ve finished all major work on the Green Line C and Mattapan Line intersection upgrades and are on schedule to complete the project 5 months earlier than originally planned.

As of October 21, 2019, we’ve replaced 6,176 feet of track, and intersection upgrades are 70% complete:

Photo Gallery

We've completed 20 out of 30 intersection upgrades. These photos show work completed on the C Line and the Mattapan Line in September and October 2019.

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects