Intersection Upgrades 60% Complete

Updated on September 16, 2019

As part of the Capital Acceleration Plan, we’ve expedited Green Line and Mattapan Line intersection upgrades to bring you a safer, more reliable MBTA experience.

We’re on schedule to complete the intersection upgrades 5 months earlier than originally planned.

As of September 2019, we've replaced 4,388 feet of track, and intersection upgrades are 60% complete:

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Photo Gallery

We've completed 18 out of 30 intersection upgrades. These photos show work completed on 1 weekend in July 2019 at Tappan and Beacon streets on the C Line.

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects