Intersection Upgrades 100% Complete

Updated on November 26, 2019

This past weekend, the Green Line Transformation team’s acceleration of the 30 intersection upgrades was completed 5 months ahead of the original schedule by maximizing planned diversions. These upgrades bring you a safer, more reliable MBTA.

In addition to accelerating the intersection upgrades, the Green Line Transformation team incorporated more than 7,000 feet of track replacement during the intersection work to leverage the service disruption for maximum results, and ultimately exceeded our goal by 1,480 feet for a total of 8,480 feet of track.

As of November 25, 2019, intersection upgrades are 100% complete:

See Work We Did November 22 – 24

This time-lapse video shows work completed at the Harvard Ave intersection on the Green Line B over the weekend of November 22 – 24, the final weekend for major intersections work.

 

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects