Second 9 Day Full Access Closure Completed

Updated on July 1, 2021

From June 24 – July 2, we shut down the Green Line D Branch between Riverside and Fenway to accelerate work on the Green Line D Track and Signal Replacement project.

During this second 9-day full access closure, crews were able to bring the overall D Branch Track and Signal project completion to 95%.

This work will enhance safety, reliability, and provide for a smoother ride on the Green Line.

What We Did: June 24 – July 2, 2021

Accelerating this project allows us to complete the most disruptive trackwork months earlier. After the second half of the 18-day closure:

  • Trackwork is 98% complete
  • Special trackwork is 99% complete
  • Signal system replacement is 91% complete.
  • Catenary Pole Foundations are 96% complete

Overall, D Branch Track and Signal project work is 95% complete

Regular Green Line service resumed as planned on July 3. From July 6 to August 5, weeknight shuttles will operate between Riverside and Reservoir from 8:45 PM to end of service.

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects

Building a Better T

As part of our $9.6 billion, 5-year capital investment plan, we're renovating stations, modernizing fare collection systems, upgrading services for our buses, subways, and ferries, and improving the accessibility of the entire system.

Learn more

Related Projects

View all projects